FOLLOW THE MONEY IN
Wyoming
5 data-center projects on file — 3.6 GW of nameplate capacity. Federal data on what residents are paying for the grid to serve them, sourced from the EIA Electric Power Monthly.
Avg residential bill
$124
/ month
Per household · 2026-02
Sales to industrial
46.1%
of state kWh
Factories + data centers · 2026-02
Residential rate rank
#42
of 51
Among the cheapest in the country
10yr rate climb
+23%
#47 of 51
Climbed slower than the US since 2016
Largest power plant
2.12 GW
· natural gas
Jim Bridger · Sweetwater County
§ 01
What residents pay
EIA · Electric Power Monthly
Wyoming · residential · latest
13.04¢/kWh
↑ +11.5% YoY
As of Single month · 2026-02
Wyoming · residential · 2026 YTD avg
12.94¢/kWh
↑ +10.6% YoY
vs 2025 YTD
US national · residential · 2026 YTD avg
17.54¢/kWh
↑ +8.5% YoY
vs 2025 YTD
§ 02
How the grid runs
Net generation · 2026-02
Where Wyoming's electricity actually comes from. Each fuel source as a share of total state generation in the most recent reported month.
WYOMING · GENERATION MIX · 2026-02
3.37 TWh net · all sectors
§ 03
Supply vs demand
EIA-860M generator inventory · projects pipeline
1.6 GW of new generation came online in Wyoming over the last 18 months; another 2.9 GW is in the EIA-860M pipeline (under construction or filed); 220 MW is on the books to retire over the next 36. Meanwhile 3.6 GW of data-center load is in construction or permitted in the state. Largest plant in the supply pipeline: Dutchman Solar Generation And Bess (Converse County) — 998 MW of solar, first online 2029-06. On the way out: Dave Johnston — 220 MW of coal, retiring 2027-12.
Two bars, one scale. Demand is sorted by certainty — under construction first, then permitted, then proposed. The dashed rule marks where the supply pipeline runs out; everything to the right of it is demand on file with no supply filed against it.
§ 04
Data-center load
5 projects
Projects on file
5
published (excludes draft / archived)
Nameplate MW
3.60 GW
≈ 16 GWh/yr at 50% load
Announced investment
—
aggregate disclosed capex
§ 05
Local voices on data centers
1 statement
SUPPORT · 2025-07
“Whoever powers the AI revolution will win the AI arms race. More American energy means data centers and AI will grow in America, not overseas. Adequate energy is not going to come from windmills and wishful thinking.”
— Sen. John Barrasso (R)SOURCE ↗
§ 07
Follow the money in Wyoming
Know when a new data center deal gets cut, who profits, and who signed off on it.
Follow the money in WY